Phase Level Budget vs. Actuals Reporting in OpenAir
Do you want to get phase level budget vs. actuals reporting in OpenAir? We have found the best way to do this is to use the project budget feature and create a “Task” level project budget. Next, create a summary report subtotaled by phase that also includes the project budget hours and the actuals value that you want to report on (i.e. actual hours invoiced). The project task budget will roll up to the phase level.